Project Launch: December 6, 2025
The successful delivery of this project highlights our ability to efficiently manage demanding construction tasks with a high level of precision, organization, and quality control. Every phase was executed in strict accordance with technical requirements and professional standards, adding another strong reference to our portfolio.
Completed right on schedule, our team navigated carefully planned and coordinated execution phases to deliver a total of 85 residential units — spanning from the initial layout to the complete final finish of the drywall systems.
More infoThe project began in March 2025. The layout for the entire building was completed in just four days. We carried out the metal framing over the course of four working weeks, followed by insulation, drywall installation, and taping. The project was successfully completed on schedule — the entire process took less than six months. The company has a strong team-oriented culture, and excellent organization and cooperation ensured that everything ran smoothly.